Overall completion
93% of 73
Essential High Medium Low
0% of 0
0% of 0
94% of 54
0% of 0

Workitem burndown

(enlarge)

"foreign" counts refer to workitems that are assigned to someone not in the team

Burndown chart

There are currently 73 workitems in 2 blueprints. The current number of workitems in each status is:

Status Count
Todo 5
Blocked 0
In Progress 0
Done 68
Postponed 0

There are 33 days left in the current cycle. That means that in order to complete all the work 0.15 workitems must be completed per day.

Topics

These are high-level goals for the cycle, which may be attained by several developers completing multiple blueprints. The progress towards each is defined by the progress towards completing all of the blueprints that contribute to implementing the Topic .



Last updated: Sun 04 December 2016, 21:37 UTC